Design Carson City Public Works

Project Description

The project display below provides a progress report for the design stages of the South Carson Street Complete Streets Project. Construction is scheduled to begin near the end of 2019.

Documents

Project Progress

60%

Overall Project Completion

  • Design Planning

    The Transportation Resource Advisory Forum for Carson City (TRAFCC) was created in order to give Carson City staff and the public a forum to discuss local transportation issues and also to educate the community about current and upcoming transportation projects. On September 22, 2016, TRAFCC was invited to attend a public planning meeting regarding the South Carson Street Corridor Study. The South Carson Street Complete Streets Corridor Study has evaluated two and a half miles of South Carson Street for conceptual design alternatives.

    20%
  • 60% Design

    The 60% design plans were completed in February. This is an exciting milestone, as the project design has started to transform from a conceptual design to a more refined and detailed project design. A thorough review of the project plans, as well as construct-ability and value engineering reviews will take place over the next month by the project team. Staff will present the 60% design at the March 13th RTC meeting with subsequent presentations at RACC and BOS meetings in April. Another public meeting/workshop is planned to be held in April (more details to come on this meeting in March).

    60%

60%

  • 40%

    Design Options Presented

    On December 3, City staff presented the design at a joint meeting with the Redevelopment Authority Citizens Committee (RACC) and Historic Resources Commission (HRC). The purpose of the presentation was to provide an update on the design of the South Carson Complete Streets Project. The Redevelopment Authority has authorized $200,000 from the Redevelopment Fund to assist in the construction of the project, including project enhancements such as landscaping, benches and other streetscape features. Staff presented conceptual designs to the Board of Supervisors on December 20, 2018. January 10, 2019 City staff met with the Historic Resources Commission and discussed any impacts that the project may have on historical and/or cultural resources. The HRC supported the project and did not anticipate any major impacts to these valuable resources. Staff has hired a consultant to further investigate and complete the appropriate environmental and historical/cultural studies.

  • 80%

    80% Design

    Design plans will be proposed for review.

20%

Design Planning

The Transportation Resource Advisory Forum for Carson City (TRAFCC) was created in order to give Carson City staff and the public a forum to discuss local transportation issues and also to educate the community about current and upcoming transportation projects. On September 22, 2016, TRAFCC was invited to attend a public planning meeting regarding the South Carson Street Corridor Study. The South Carson Street Complete Streets Corridor Study has evaluated two and a half miles of South Carson Street for conceptual design alternatives.

40%

Design Options Presented

On December 3, City staff presented the design at a joint meeting with the Redevelopment Authority Citizens Committee (RACC) and Historic Resources Commission (HRC). The purpose of the presentation was to provide an update on the design of the South Carson Complete Streets Project. The Redevelopment Authority has authorized $200,000 from the Redevelopment Fund to assist in the construction of the project, including project enhancements such as landscaping, benches and other streetscape features. Staff presented conceptual designs to the Board of Supervisors on December 20, 2018. January 10, 2019 City staff met with the Historic Resources Commission and discussed any impacts that the project may have on historical and/or cultural resources. The HRC supported the project and did not anticipate any major impacts to these valuable resources. Staff has hired a consultant to further investigate and complete the appropriate environmental and historical/cultural studies.

60%

60% Design

The 60% design plans were completed in February. This is an exciting milestone, as the project design has started to transform from a conceptual design to a more refined and detailed project design. A thorough review of the project plans, as well as construct-ability and value engineering reviews will take place over the next month by the project team. Staff will present the 60% design at the March 13th RTC meeting with subsequent presentations at RACC and BOS meetings in April. Another public meeting/workshop is planned to be held in April (more details to come on this meeting in March).

80%

80% Design

Design plans will be proposed for review.

1. Probable Cost Estimate Complete 100%

100%
Description
Carson City Infrastructure Tax Funds & Local Funds $5,136,118- 27%
Nevada Department of Transportation $5,128,847- 27%
Other State Funds $1,122,372 - 6%
TIGER $7,570,202- 40%
Total $18,957,539 100%

2. Public Planning Meetings Complete 50%

50%
Description
PUBLIC MEETING #1 As part of the project, public outreach was critical to identifying a community-preferred cross section for South Carson Street. The purpose of the first public meeting was to obtain information on the types of improvements that the community would like to see along the corridor. The first public meeting was on Thursday, September 22, 2016, from 5:00 PM to 7:00 PM at Fuji Park.
PUBLIC MEETING #2 After the cross section alternatives were developed, a second public meeting was conducted. The second public meeting was held on Wednesday, March 1, 2017, at the Carson City Community Center. In addition to traditional methods of notifying the community about the meeting, CAMPO mailed information to those along the corridor, and distributed information to businesses along the corridor.
PUBLIC MEETING #3 The meeting was Tuesday, December 11, 2018, from 4:30 p.m. to 7:00 p.m. at the Carson City Sheriff’s Office Ormsby Room. The meeting included a presentation on the South Carson Street 30% preliminary design plans, project schedule, and discuss various communication tools for the public to stay connected during the design and construction process. The public used the opportunity to provide input on the development of the South Carson Street corridor.

3. Design Complete 60%

60%
Description
The 60% design plans were completed in February. This is an exciting milestone, as the project design has started to transform from a conceptual design to a more refined and detailed project design. A thorough review of the project plans, as well as construct-ability and value engineering reviews will take place over the next month by the project team. Staff will present the 60% design at the March 13th RTC meeting with subsequent presentations at RACC and BOS meetings in April. Another public meeting/workshop is planned to be held in April (more details to come on this meeting in March).

Comments are closed.